Bill Of Quantities Total Calculator

Work out bill of quantities total instantly with clear inputs, formula shown and shareable results.

About Bill Of Quantities Total Calculator

A bill of quantities totals the priced measured work section by section, then adds a contingency for undefined risk. Looking at which section dominates the total shows where estimating error hurts most, and where value engineering effort should be concentrated.

Formula

Bill total

Total = sum of section values x (1 + contingency percentage)

Worked example

With the default values below, Bill Of Quantities Total Calculator returns Bill of quantities total of $551,250.00. Change any input above and every figure here is recalculated in your browser.

Inputs used

Substructure and civil worksminimum 0
250,000
Superstructure and finishesminimum 0
180,000
Services and external worksminimum 0
95,000
Contingencyaccepts 0–30 %
5 %

Results

Bill of quantities total
$551,250.00
Measured works subtotal
$525,000.00
Contingency sum
$26,250.00
Largest section share
47.6% %

Step by step

  1. 1Values used
  2. 2Bill total
  3. 3Bill of quantities total= 551,250.00
  4. 4Measured works subtotal= 525,000.00
  5. 5Contingency sum= 26,250.00
  6. 6Largest section share= 47.6 %

Assumptions and limits

  • The result is derived only from the 4 inputs listed above. Anything not among them is not part of the calculation.
  • In particular, this calculator does not take inflation, tax, fees or charges or compounding frequency into account.
  • Figures are rounded for display to 2 decimal places, so totals built from several rounded parts can differ slightly from the unrounded arithmetic.

How these calculators are built and tested is described on the Methodology page. If a figure looks wrong, please report it.

Frequently Asked Questions

How is the Bill Of Quantities Total figure worked out?

Total = sum of section values x (1 + contingency percentage). A bill of quantities totals the priced measured work section by section, then adds a contingency for undefined risk.

How large should the contingency be?

It reflects design maturity: 10-15 percent at concept, 5-10 percent at detailed design and 2-5 percent on a fully documented tender. Carrying a large contingency on a well defined job just inflates the budget.

What values do I need to enter?

This calculator takes 4 inputs: Substructure and civil works, Superstructure and finishes, Services and external works, Contingency. The pre-filled defaults are a realistic worked example — replace them with your own site or project figures.