Bill Of Quantities Total Calculator
Work out bill of quantities total instantly with clear inputs, formula shown and shareable results.
About Bill Of Quantities Total Calculator
A bill of quantities totals the priced measured work section by section, then adds a contingency for undefined risk. Looking at which section dominates the total shows where estimating error hurts most, and where value engineering effort should be concentrated.
Formula
Bill total
Total = sum of section values x (1 + contingency percentage)
Worked example
With the default values below, Bill Of Quantities Total Calculator returns Bill of quantities total of $551,250.00. Change any input above and every figure here is recalculated in your browser.
Inputs used
- Substructure and civil worksminimum 0
- 250,000
- Superstructure and finishesminimum 0
- 180,000
- Services and external worksminimum 0
- 95,000
- Contingencyaccepts 0–30 %
- 5 %
Results
- Bill of quantities total
- $551,250.00
- Measured works subtotal
- $525,000.00
- Contingency sum
- $26,250.00
- Largest section share
- 47.6% %
Step by step
- 1Values used
- 2Bill total
- 3Bill of quantities total= 551,250.00
- 4Measured works subtotal= 525,000.00
- 5Contingency sum= 26,250.00
- 6Largest section share= 47.6 %
Assumptions and limits
- The result is derived only from the 4 inputs listed above. Anything not among them is not part of the calculation.
- In particular, this calculator does not take inflation, tax, fees or charges or compounding frequency into account.
- Figures are rounded for display to 2 decimal places, so totals built from several rounded parts can differ slightly from the unrounded arithmetic.
How these calculators are built and tested is described on the Methodology page. If a figure looks wrong, please report it.
Frequently Asked Questions
How is the Bill Of Quantities Total figure worked out?
Total = sum of section values x (1 + contingency percentage). A bill of quantities totals the priced measured work section by section, then adds a contingency for undefined risk.
How large should the contingency be?
It reflects design maturity: 10-15 percent at concept, 5-10 percent at detailed design and 2-5 percent on a fully documented tender. Carrying a large contingency on a well defined job just inflates the budget.
What values do I need to enter?
This calculator takes 4 inputs: Substructure and civil works, Superstructure and finishes, Services and external works, Contingency. The pre-filled defaults are a realistic worked example — replace them with your own site or project figures.
Related Calculators
You might also need
- Aggregate Tonnage CalculatorAlso in Construction & Civil Engineering
- Asphalt Quantity CalculatorAlso in Construction & Civil Engineering
- Asphalt Tonnage CalculatorAlso in Construction & Civil Engineering
- Backfill Quantity CalculatorAlso in Construction & Civil Engineering
- Beam Load CalculatorAlso in Construction & Civil Engineering
- Building Depreciation CalculatorAlso in Construction & Civil Engineering
