Work out ready mix concrete order instantly with clear inputs, formula shown and shareable results.

About Ready Mix Concrete Order Calculator

Ready mix is ordered on gross volume: the measured requirement plus a wastage allowance of five to ten percent for pump priming, spillage, over-dig and the concrete left in the drum. Dividing by truck capacity gives the number of loads, which matters because part loads usually attract a surcharge.

Formulas

Order volume

V order = net volume x (1 + wastage)

Loads and cost

Loads = ceil(V order / truck capacity); cost = V order x unit price

Worked example

With the default values below, Ready Mix Concrete Order Calculator returns Estimated concrete cost of $1,219.80. Change any input above and every figure here is recalculated in your browser.

Inputs used

Net concrete volumeminimum 0.1 m³
12 m³
Wastage allowanceaccepts 0–30 %
7 %
Truck mixer capacityminimum 0.5 m³
6 m³
Price per cubic metreminimum 0.01
95

Results

Estimated concrete cost
$1,219.80
Volume to order
12.84 m³
Truck loads required
3
Wastage allowance
0.84 m³

Step by step

  1. 1Values used
  2. 2Order volume
  3. 3Loads and cost
  4. 4Estimated concrete cost= 1,219.80
  5. 5Volume to order= 12.84 m³
  6. 6Truck loads required= 3
  7. 7Wastage allowance= 0.84 m³

Assumptions and limits

  • The result is derived only from the 4 inputs listed above. Anything not among them is not part of the calculation.
  • In particular, this calculator does not take inflation, tax, fees or charges or compounding frequency into account.
  • Figures are rounded for display to 2 decimal places, so totals built from several rounded parts can differ slightly from the unrounded arithmetic.

How these calculators are built and tested is described on the Methodology page. If a figure looks wrong, please report it.

Frequently Asked Questions

How is the Ready Mix Concrete Order figure worked out?

V order = net volume x (1 + wastage). Ready mix is ordered on gross volume: the measured requirement plus a wastage allowance of five to ten percent for pump priming, spillage, over-dig and the concrete left in the drum.

Why not order exactly what is measured?

Running short mid-pour creates a cold joint, which is far more expensive to remedy than a small surplus. Ordering slightly over is standard practice.

What values do I need to enter?

This calculator takes 4 inputs: Net concrete volume, Wastage allowance, Truck mixer capacity, Price per cubic metre. The pre-filled defaults are a realistic worked example — replace them with your own site or project figures.