Release Burndown Calculator
Track release burndown, scope creep and the projected completion date.
About Release Burndown Calculator
Projecting from observed velocity rather than planned velocity is what makes a burndown predictive. Tracking added scope separately shows whether a slipping date is a delivery problem or a scope problem. Scope creep and slow delivery need opposite responses, and a burndown that hides added scope makes them indistinguishable.
Formula
Release Burndown
Projected sprints = elapsed + remaining points ÷ observed velocity
- scope creep
- Work added after the release scope was agreed
- observed velocity
- Completed points divided by sprints elapsed
Worked example
With the default values below, Release Burndown Calculator returns Projected Total Sprints of 11.50. Change any input above and every figure here is recalculated in your browser.
Inputs used
- Original scopeminimum 0
- 300
- Scope added since startminimum 0
- 45
- Points completedminimum 0
- 180
- Sprints elapsedminimum 0.1
- 6
- Sprints plannedminimum 0.1
- 10
Results
- Projected Total Sprints
- 11.50
- Points Remaining
- 165
- Scope Creep
- 15.00%
- Completion
- 52.17%
- Verdict
- Slightly behind plan
Step by step
- 1Values used
- 2Release Burndown
- 3Projected Total Sprints= 11.50
- 4Points Remaining= 165
- 5Scope Creep= 15.00
- 6Completion= 52.17
- 7Verdict= Slightly behind plan
Assumptions and limits
- The result is derived only from the 5 inputs listed above. Anything not among them is not part of the calculation.
- In particular, this calculator does not take inflation, tax, fees or charges or compounding frequency into account.
- Figures are rounded for display to 2 decimal places, so totals built from several rounded parts can differ slightly from the unrounded arithmetic.
How these calculators are built and tested is described on the Methodology page. If a figure looks wrong, please report it.
Frequently Asked Questions
How is Release Burndown calculated?
Projected sprints = elapsed + remaining points ÷ observed velocity Projecting from observed velocity rather than planned velocity is what makes a burndown predictive. Tracking added scope separately shows whether a slipping date is a delivery problem or a scope problem.
Why does Release Burndown matter?
Scope creep and slow delivery need opposite responses, and a burndown that hides added scope makes them indistinguishable.
What values do I need to enter?
This calculator takes 5 inputs: Original scope, Scope added since start, Points completed, Sprints elapsed, Sprints planned. The pre-filled defaults are a realistic starting point — replace them with figures from your own environment for a result you can act on.
Related Calculators
You might also need
- Database Connection Pool CalculatorCommonly used together
- Elasticsearch Shard CalculatorCommonly used together
- Redis Memory CalculatorCommonly used together
- Password GeneratorAlso in Developer & Networking
- 4K Streaming DataAlso in Developer & Networking
- Accessibility Contrast CalculatorAlso in Developer & Networking