Skip to content
Calcrivo

Sprint Burndown Calculator

Calculate remaining sprint work and team velocity from total story points, completed points and sprint count.

Inputs

points

Total story points planned for the sprint (or release).

points

Story points completed so far.

sprints

Number of sprints elapsed so far, used to compute velocity.

days

Working days left in the current sprint, for a daily burn rate needed.

Remaining Story Points

28points

Team Velocity

26.0points/sprint

Percent Complete

65.0%

Sprints Remaining at Current Velocity

1.08sprints

Required Daily Burn Rate

7.00points/day

Step by step

  1. Remaining: total − completed

    80 − 52

    = 28 points

  2. Velocity: completed ÷ sprints elapsed

    52 ÷ 2

    = 26.0 points/sprint

  3. Sprints remaining at current velocity

    28 ÷ 26.0

    = 1.08 sprints

How it works

Sprint burndown tracks work remaining against the team's demonstrated pace: remaining = total_points − completed_points, velocity = completed_points ÷ sprints_elapsed. Projecting remaining work forward at the current velocity estimates how many more sprints are needed at the current pace, while the required daily burn rate shows what pace is needed to finish the current sprint's remaining work in the days left.

Formula

ideal_remaining = total_points × (1 - elapsed_days / sprint_days)

total_points
Total story points committed for the sprint
elapsed_days
Days elapsed in the sprint
sprint_days
Total sprint duration (days)

Frequently Asked Questions

Why measure velocity across multiple sprints instead of just the current one?

Velocity from a single sprint can be skewed by holidays, one-off distractions, or estimation variance; averaging completed points across several recent sprints gives a more stable, representative pace for forecasting.

What does it mean if the required daily burn rate greatly exceeds current velocity?

It signals the current sprint's remaining work likely won't be finished in the time left at the team's historical pace — either the scope needs to be trimmed, more capacity needs to be added, or the sprint goal needs to be renegotiated.

Should story points be comparable across different teams?

No — story points are a relative, team-specific estimation unit; comparing velocity in points directly between teams is a common anti-pattern since each team's point scale is calibrated differently.

How does burndown differ from burnup?

A burndown chart shows remaining work trending toward zero over time; a burnup chart shows completed work trending toward the total scope line — burnup has the advantage of visibly showing scope changes (the total line moving) that burndown can obscure.

You might also need