Waterproofing Area Calculator
Work out waterproofing area instantly with clear inputs, formula shown and shareable results.
About Waterproofing Area Calculator
Waterproofing area is the horizontal surface plus the upstand carried up the walls, perimeter times upstand height, which is where most failures actually occur. Liquid systems multiply that area by the number of coats, while sheet membrane needs a 15 percent allowance for laps.
Formulas
Area
Total m² = floor area + perimeter x upstand height
Quantities
Liquid coats = total x coats; membrane rolls = ceil(total x 1.15 / roll area)
Worked example
With the default values below, Waterproofing Area Calculator returns Area to waterproof of 47.80. Change any input above and every figure here is recalculated in your browser.
Inputs used
- Floor areaminimum 0.1 m²
- 40 m²
- Perimeterminimum 0 m
- 26 m
- Upstand heightminimum 0 m
- 0.3 m
- Number of coatsminimum 1
- 2
Results
- Area to waterproof
- 47.80 m²
- Upstand area
- 7.80 m²
- Total coated area
- 95.60 m²
- Membrane rolls at 10 m²
- 6
Step by step
- 1Values used
- 2Area
- 3Quantities
- 4Area to waterproof= 47.80 m²
- 5Upstand area= 7.80 m²
- 6Total coated area= 95.60 m²
- 7Membrane rolls at 10 m²= 6
Assumptions and limits
- The result is derived only from the 4 inputs listed above. Anything not among them is not part of the calculation.
- In particular, this calculator does not take inflation, tax, fees or charges or compounding frequency into account.
- Figures are rounded for display to 2 decimal places, so totals built from several rounded parts can differ slightly from the unrounded arithmetic.
How these calculators are built and tested is described on the Methodology page. If a figure looks wrong, please report it.
Frequently Asked Questions
How is the Waterproofing Area figure worked out?
Total m² = floor area + perimeter x upstand height. Waterproofing area is the horizontal surface plus the upstand carried up the walls, perimeter times upstand height, which is where most failures actually occur.
How high should the upstand be?
At least 150 mm above finished floor level generally, and 1.8 m or more in shower zones. Terminating below the wet zone simply relocates the leak.
What values do I need to enter?
This calculator takes 4 inputs: Floor area, Perimeter, Upstand height, Number of coats. The pre-filled defaults are a realistic worked example — replace them with your own site or project figures.
Related Calculators
You might also need
- Built Up Area CalculatorAlso in Construction & Civil Engineering
- Formwork Area CalculatorAlso in Construction & Civil Engineering
- Aggregate Tonnage CalculatorAlso in Construction & Civil Engineering
- Asphalt Quantity CalculatorAlso in Construction & Civil Engineering
- Asphalt Tonnage CalculatorAlso in Construction & Civil Engineering
- Backfill Quantity CalculatorAlso in Construction & Civil Engineering