Annotation schedules slip because planners use nominal working hours rather than productive ones. Effective capacity is annotators multiplied by genuinely productive hours per day — typically six of eight once breaks, guideline lookups and edge-case discussion are removed — and the calendar duration is total work divided by that capacity.
Schedule
total hours = items x seconds / 3600; daily capacity = annotators x productive hours; days = total hours / daily capacity
Sustained annotation is fatiguing and quality falls sharply after a few hours. Teams that plan on eight hours routinely finish late and with worse agreement.
Only up to a point. Larger teams need more guideline training and more adjudication, and consistency drops, so plan for a modest efficiency loss as the team grows.