Count fabric and access cables for a leaf-spine build, including a spares allowance.

Inputs

switches
switches
links
servers
ports
%

Cables to Order

1,549cables

Leaf-to-Spine Cables

128cables

Server Access Cables

1,280cables

Spare Cables Included

141cables

Cables in Service

1,408cables

Step by step

  1. Values used

    Leaf switches = 16 switches; Spine switches = 4 switches; Links between each leaf and spine = 2 links; Servers per leaf = 40 servers; NIC ports per server = 2 ports; Spares allowance = 10 %

  2. Cable Count

    fabric cables = leaves × spines × links per pair; access cables = leaves × servers per leaf × NIC ports; add the spares percentage.

  3. Cables to Order

    = 1,549 cables

  4. Leaf-to-Spine Cables

    = 128 cables

  5. Server Access Cables

    = 1,280 cables

  6. Spare Cables Included

    = 141 cables

  7. Cables in Service

    = 1,408 cables

How it works

A full-mesh leaf-spine needs one cable from every leaf to every spine for each parallel link, which grows as the product of the two tiers. Access cabling is per NIC port, and a 10% spares allowance covers breakage and moves. Cabling is often the largest single line item and the longest lead time in a fabric build, and a recount after installation starts is expensive.

Formula

Cable Count

fabric cables = leaves × spines × links per pair; access cables = leaves × servers per leaf × NIC ports; add the spares percentage.

links per pair
Parallel cables between one leaf and one spine
spares
Allowance for damaged, mislabelled and future cables

Frequently Asked Questions

How is Cable Count calculated?

fabric cables = leaves × spines × links per pair; access cables = leaves × servers per leaf × NIC ports; add the spares percentage. A full-mesh leaf-spine needs one cable from every leaf to every spine for each parallel link, which grows as the product of the two tiers. Access cabling is per NIC port, and a 10% spares allowance covers breakage and moves.

Why does Cable Count matter?

Cabling is often the largest single line item and the longest lead time in a fabric build, and a recount after installation starts is expensive.

What values do I need to enter?