Cement Sand Aggregate Quantity Calculator
Work out cement sand aggregate quantity instantly with clear inputs, formula shown and shareable results.
About Cement Sand Aggregate Quantity Calculator
Dry materials occupy more space than the concrete they produce because water fills the voids, so wet volume is multiplied by about 1.54 to get dry volume. That dry volume is then split by the nominal mix parts. Cement volume is converted to bags using a bulk density of 1440 kg/m³ and 50 kg per bag.
Formulas
Dry volume
Dry = wet volume x 1.54
Material split
Each material = dry volume x its part / sum of parts; cement bags = cement m³ x 1440 / 50
Worked example
With the default values below, Cement Sand Aggregate Quantity Calculator returns Cement required of 80.6. Change any input above and every figure here is recalculated in your browser.
Inputs used
- Wet concrete volumeminimum 0.01 m³
- 10 m³
- Nominal mixone of M15 — 1 : 2 : 4, M20 — 1 : 1.5 : 3, M25 — 1 : 1 : 2
- M20 — 1 : 1.5 : 3
- Dry volume factoraccepts 1–2
- 1.54
Results
- Cement required
- 80.6 bags
- Fine aggregate
- 4.200 m³
- Coarse aggregate
- 8.400 m³
- Dry volume of materials
- 15.400 m³
Step by step
- 1Values used
- 2Dry volume
- 3Material split
- 4Cement required= 80.6 bags
- 5Fine aggregate= 4.200 m³
- 6Coarse aggregate= 8.400 m³
- 7Dry volume of materials= 15.400 m³
Assumptions and limits
- The result is derived only from the 3 inputs listed above. Anything not among them is not part of the calculation.
- In particular, this calculator does not take inflation, tax, fees or charges or compounding frequency into account.
- Figures are rounded for display to 3 decimal places, so totals built from several rounded parts can differ slightly from the unrounded arithmetic.
How these calculators are built and tested is described on the Methodology page. If a figure looks wrong, please report it.
Frequently Asked Questions
How is the Cement Sand Aggregate Quantity figure worked out?
Dry = wet volume x 1.54. Dry materials occupy more space than the concrete they produce because water fills the voids, so wet volume is multiplied by about 1.54 to get dry volume.
Why 1.54 and not 1.52 or 1.57?
The factor covers bulking of sand and the voids in the aggregate, both of which vary with grading and moisture. Anything between 1.52 and 1.57 is defensible; 1.54 is the common site value.
What values do I need to enter?
This calculator takes 3 inputs: Wet concrete volume, Nominal mix, Dry volume factor. The pre-filled defaults are a realistic worked example — replace them with your own site or project figures.
Related Calculators
You might also need
- Sand Quantity CalculatorAlso in Construction & Civil Engineering
- Plaster Sand And Cement CalculatorAlso in Construction & Civil Engineering
- Aggregate Tonnage CalculatorAlso in Construction & Civil Engineering
- Asphalt Quantity CalculatorAlso in Construction & Civil Engineering
- Backfill Quantity CalculatorAlso in Construction & Civil Engineering
- Hardcore Quantity CalculatorAlso in Construction & Civil Engineering