Pavement Design (CBR) Calculator
Work out pavement design (cbr) instantly with clear inputs, formula shown and shareable results.
About Pavement Design (CBR) Calculator
The CBR method sizes a flexible pavement from soaked subgrade strength and cumulative standard axles. Thickness grows with the logarithm of traffic and falls as CBR rises, scaled here from a 400 mm reference for 10 msa on a CBR 5 subgrade. The correlation E = 17.6 CBR^0.64 converts CBR to an elastic modulus for mechanistic checks.
Formulas
Total thickness
T mm = 200 x (log10 msa + 1) x (5 / CBR)^0.4
Subgrade modulus
E MPa = 17.6 x CBR^0.64
Worked example
With the default values below, Pavement Design (CBR) Calculator returns Total pavement thickness of 400. Change any input above and every figure here is recalculated in your browser.
Inputs used
- Soaked subgrade CBRaccepts 1–40 %
- 5 %
- Cumulative design trafficminimum 0.1 msa
- 10 msa
- Bituminous layer thicknessminimum 20 mm
- 80 mm
Results
- Total pavement thickness
- 400 mm
- Granular layers thickness
- 320 mm
- Estimated subgrade modulus
- 49.3 MPa
- Design note
- Moderate subgrade, standard design applies
Step by step
- 1Values used
- 2Total thickness
- 3Subgrade modulus
- 4Total pavement thickness= 400 mm
- 5Granular layers thickness= 320 mm
- 6Estimated subgrade modulus= 49.3 MPa
- 7Design note= Moderate subgrade, standard design applies
Assumptions and limits
- The result is derived only from the 3 inputs listed above. Anything not among them is not part of the calculation.
- In particular, this calculator does not take inflation, tax, fees or charges or compounding frequency into account.
- Figures are rounded for display to 1 decimal place, so totals built from several rounded parts can differ slightly from the unrounded arithmetic.
- Preliminary estimate only. Pavement design must follow the design guide adopted by the road authority and be verified by a qualified highway engineer.
How these calculators are built and tested is described on the Methodology page. If a figure looks wrong, please report it.
Preliminary estimate only. Pavement design must follow the design guide adopted by the road authority and be verified by a qualified highway engineer.
Frequently Asked Questions
How is the Pavement Design (CBR) figure worked out?
T mm = 200 x (log10 msa + 1) x (5 / CBR)^0.4. The CBR method sizes a flexible pavement from soaked subgrade strength and cumulative standard axles.
Why is CBR tested soaked?
Because the design condition is the worst credible moisture state. A subgrade tested at optimum moisture can show three times the soaked CBR and would produce a dangerously thin pavement.
What values do I need to enter?
This calculator takes 3 inputs: Soaked subgrade CBR, Cumulative design traffic, Bituminous layer thickness. The pre-filled defaults are a realistic worked example — replace them with your own site or project figures.
Related Calculators
- Area By Coordinates Calculator
- Area By Double Meridian Distance Calculator
- Bearing And Distance From Coordinates Calculator
- Betterment Levy Calculator
- Building Height Limit From Road Width Calculator
- Bus Frequency Requirement Calculator
- Chain Survey Offset Calculator
- Compensation For Land Calculator
- Contour Volume (Prismoidal) Calculator
- Coordinate Transformation Calculator
You might also need
- Area By Coordinates CalculatorAlso in Surveying, GIS & Urban Planning
- Betterment Levy CalculatorAlso in Surveying, GIS & Urban Planning
- Coordinate Transformation CalculatorAlso in Surveying, GIS & Urban Planning
- Development Charges CalculatorAlso in Surveying, GIS & Urban Planning
- Intersection Delay CalculatorAlso in Surveying, GIS & Urban Planning
- Parking Turnover CalculatorAlso in Surveying, GIS & Urban Planning