Redundancy Reliability Calculator
Work out redundancy reliability instantly with clear inputs, formula shown and shareable results.
About Redundancy Reliability Calculator
For k-out-of-n redundancy the system works if at least k of n units work, giving the binomial sum of terms C(n,k) R^k (1-R)^(n-k) from k to n. Full parallel redundancy is the special case k = 1, where system unreliability is (1-R)^n — three units at 92% each give 99.95% availability.
Formulas
k-out-of-n reliability
R_system = sum from k to n of C(n,k) x R^k x (1-R)^(n-k)
Full parallel
R_system = 1 - (1 - R)^n
Worked example
With the default values below, Redundancy Reliability Calculator returns System Reliability of 99.94880%. Change any input above and every figure here is recalculated in your browser.
Inputs used
- Reliability Of One Unitaccepts 0.1–99.999 %
- 92 %
- Units In Parallelaccepts 1–20
- 3
- Units Required To Functionaccepts 1–20
- 1
- Cost Per Unitminimum 0
- 180,000
Results
- System Reliability
- 99.94880%
- Gain Over A Single Unit
- 7.9488%
- Cost Of Redundant Set
- $540,000.00
- System Unavailability
- 0.05120%
Step by step
- 1Values used
- 2k-out-of-n reliability
- 3Full parallel
- 4System Reliability= 99.94880
- 5Gain Over A Single Unit= 7.9488
- 6Cost Of Redundant Set= 540,000.00
- 7System Unavailability= 0.05120
Assumptions and limits
- The result is derived only from the 4 inputs listed above. Anything not among them is not part of the calculation.
- In particular, this calculator does not take inflation, tax or compounding frequency into account.
- Figures are rounded for display to 5 decimal places, so totals built from several rounded parts can differ slightly from the unrounded arithmetic.
How these calculators are built and tested is described on the Methodology page. If a figure looks wrong, please report it.
Frequently Asked Questions
Does redundancy always deliver the calculated gain?
Only if failures are independent. Common-cause failures — shared power supply, shared cooling, identical design defect — bypass redundancy entirely and often dominate real system unavailability.
Is 2-out-of-3 better than 1-out-of-2?
For availability, 1-out-of-2 is better. For safety systems that must avoid false trips as well as failures to act, 2-out-of-3 voting balances both, which is why it is standard in process safety.
Related Calculators
- Reliability At Time T Calculator
- Weibull Reliability Estimate Calculator
- 5S Audit Score Calculator
- Accelerated Ageing Time Calculator
- Acceptance Number (AQL) Calculator
- Availability And Performance Rate Calculator
- Batch Size Optimisation Calculator
- Bathtub Curve Failure Rate Calculator
- Bottle Fill Volume Calculator
- Bottleneck Identification Calculator
You might also need
- Reliability At Time T CalculatorAlso in Manufacturing, Packaging & Textiles
- Weibull Reliability Estimate CalculatorAlso in Manufacturing, Packaging & Textiles
- 5S Audit Score CalculatorAlso in Manufacturing, Packaging & Textiles
- Bottleneck Identification CalculatorAlso in Manufacturing, Packaging & Textiles
- Calibration Interval CalculatorAlso in Manufacturing, Packaging & Textiles
- Cap Torque CalculatorAlso in Manufacturing, Packaging & Textiles