Burndown Projection Calculator
Work out burndown projection instantly with clear inputs, formula shown and shareable results.
About Burndown Projection Calculator
A burndown projection must subtract scope growth from velocity, because work added each sprint offsets work completed. Ignoring scope creep is the single most common reason burndown forecasts prove optimistic, and the net velocity figure makes the effect explicit.
Formulas
Net velocity
Net velocity = Average velocity - Scope added per sprint
Sprints to completion
Sprints = Remaining points / Net velocity
Worked example
With the default values below, Burndown Projection Calculator returns Sprints to completion of 5.17. Change any input above and every figure here is recalculated in your browser.
Inputs used
- Remaining story points
- 186
- Average velocity per sprint
- 42
- Scope added per sprint (points)
- 6
- Sprint length
- 10 days
Results
- Sprints to completion
- 5.17
- Calendar days to completion
- 52
- Net velocity after scope creep
- 36.00
- Extra sprints caused by scope creep
- 0.74
Step by step
- 1Values used
- 2Net velocity
- 3Sprints to completion
- 4Sprints to completion= 5.17
- 5Calendar days to completion= 52
- 6Net velocity after scope creep= 36.00
- 7Extra sprints caused by scope creep= 0.74
Assumptions and limits
- The result is derived only from the 4 inputs listed above. Anything not among them is not part of the calculation.
- In particular, this calculator does not take inflation, fees or charges or compounding frequency into account.
- Figures are rounded for display to 2 decimal places, so totals built from several rounded parts can differ slightly from the unrounded arithmetic.
How these calculators are built and tested is described on the Methodology page. If a figure looks wrong, please report it.
Frequently Asked Questions
What if scope growth exceeds velocity?
Then the backlog never burns down. That is a scope management problem, not a delivery problem, and no amount of extra effort fixes it.
Should I use average or worst-case velocity?
Present a range: best case on the highest recent velocity, worst case on the lowest. A single-point date will be wrong.
Related Calculators
You might also need
- CGPA CalculatorAlso in Work, Career, HR & Education Admin
- eNPS CalculatorAlso in Work, Career, HR & Education Admin
- SGPA CalculatorAlso in Work, Career, HR & Education Admin
- Appraisal Score CalculatorAlso in Work, Career, HR & Education Admin
- Apprenticeship Wage CalculatorAlso in Work, Career, HR & Education Admin
- CGPA To Percentage CalculatorAlso in Work, Career, HR & Education Admin