About OKR Progress Calculator

OKR progress is measured from the starting baseline to the target, not from zero, which is what makes a key result honest. Comparing progress with the proportion of the quarter elapsed converts a raw percentage into a pace judgment.

Formulas

Progress

Progress % = (Current - Starting) / (Target - Starting) x 100

Expected progress

Expected % = Weeks elapsed / 13 x 100

Worked example

With the default values below, OKR Progress Calculator returns Key result progress of 50.00%. Change any input above and every figure here is recalculated in your browser.

Inputs used

Starting value
1,200
Current value
2,600
Target value
4,000
Weeks elapsed in the quarter
8

Results

Key result progress
50.00%
Expected progress by now
61.54%
Ahead or behind pace
-11.54%
Confidence grade
At risk — amber

Step by step

  1. 1Values used
  2. 2Progress
  3. 3Expected progress
  4. 4Key result progress= 50.00
  5. 5Expected progress by now= 61.54
  6. 6Ahead or behind pace= -11.54
  7. 7Confidence grade= At risk — amber

Assumptions and limits

  • The result is derived only from the 4 inputs listed above. Anything not among them is not part of the calculation.
  • In particular, this calculator does not take inflation, tax, fees or charges or compounding frequency into account.
  • Figures are rounded for display to 2 decimal places, so totals built from several rounded parts can differ slightly from the unrounded arithmetic.

How these calculators are built and tested is described on the Methodology page. If a figure looks wrong, please report it.

Frequently Asked Questions

Why measure from the baseline?

Because a key result that moves a metric from 1,200 to 4,000 has achieved nothing at 1,200. Measuring from zero would show 30% progress on day one.

What does 70% mean in OKR practice?

For deliberately ambitious objectives, 70% is considered success. Consistently hitting 100% suggests the targets are not stretching.